| 
  
 Summer 2003 (11.2)
 Page
      69
 Progress At McDermott
 Activities
      at the Shipyards
 
 
   Left: The Baku Deep Water Jacket Factory where McDermott's
      projects are being constructed. 
 Guloghlan Nazarov, 47,
      still remembers the spring day back in 1992 when he first met
      representatives of McDermott Caspian Contractors Inc. (MCCI),
      the Caspian operating subsidiary of J. Ray McDermott S.A. "I
      had been working at the Baku Deepwater Fabrication Factory for
      nearly 10 years and was anxious about the changes that were taking
      place at the factory and about its future," he recalls.
 
 It was very difficult time for the Baku Deepwater Jacket Factory
      (BDJF), and Azerbaijan's economy had been affected by social
      and economic problems just like all the other newly independent
      republics after the collapse of the Soviet Union. "Being
      a master mechanic at the factory, I had always worked closely
      with MCCI. After a while, I became convinced that their presence
      would revive the facility that had been one of the largest and
      most modern industrial units in the region. I'm so glad my intuition
      was right," says Nazarov.
 
 Guloghlan was one of hundreds of Azerbaijani professionals participating
      in MCCI's previous fabrication activities in the Caspian as a
      contractor for AIOC's Early Oil Project in 1997. Shortly after
      that project was completed, Guloghlan returned to work for BDJF,
      which, by that time, had been renamed ShelfProjectStroi (SPS).
 
 Then when MCCI was awarded a new contract for AIOC's Phase 1
      of the Azeri Project in 2001, Guloghlan was invited to rejoin
      MCCI as Equipment Maintenance Superintendent. "It sounds
      confusing, doesn't it?" asks Guloghlan rhetorically: "During
      the last ten years, I've worked for BDJF, MCCI, SPS and MCCI
      again, but in reality I've never moved from the fabrication area
      where I started more than 20 years ago as a graduate of Kiev
      Polytechnic University!"
 
 
   Left: Guloghlan Nazarov who works at the shipyards. 
 The changes I've seen
      since I rejoined MCCI in January 2002 are amazing," says
      Guloghlan. In October 2002, MCCI signed new contracts with AIOC
      for the fabrication of two integrated topside decks - West Azeri
      (WA) and East Azeri (EA) - for Phase 2 of the Azeri Project,
      and the installation of the 28-inch gas trunkline from the Azeri
      field to the Sangachal Terminal. The size of the two decks, WA
      and EA weigh approximately 15,500MT each.
 
 Earlier in November 2001 MCCI was involved with the fabrication
      and installation of Central Azeri (CA) 14,000MT integrated deck
      and offshore installation of 187km of export pipeline for Phase
      1 of the Azeri Project.
 
 MCCI with BDJF are forming a new Azerbaijan company, Caspian
      Offshore Fabricators, LLC (COFLLC) to carry out the work for
      the fabrication of decks. MCCI will provide COFLLC with its technology,
      proven in-house resources, development experience and project
      management expertise to manage and build project facilities.
      BDJF will contribute the required fabrication facilities and
      skilled personnel.
 
 "Upgrades and fabrication work have commenced on the WA
      contract and are currently ahead of schedule," said Clint
      Anderson, Vice President of MCCI. "A full infrastructure
      is being established at the BDJF yard after the comprehensive
      Phase 1 upgrade program where we undertook work valued at more
      than US $20 million to refurbish the existing facilities,"
      said Anderson.
 
 "By the end of April 2003, our work on the CA contract approached
      the mid-point of the schedule and the project is on track for
      Sailaway at the end of June 2004", explained Anderson. "Although
      the upgrades scope of work of KMNF's pipelay barge, the "Israfil
      Huseynov", which we are also commissioned to execute by
      AIOC has turned out to be larger than we initially expected,
      we are optimistic that the barge will depart for sea trials towards
      the end of May 2003."
 
 The barge upgrade has required more than 600,000 MCCI direct
      labor and subcontractor man-hours over the last 14 months. The
      offshore installation scope of pipelay includes approximately
      400km of oil export lines, gas lines and in-field lines, with
      approximately 31,500 pipe joints of 30-, 28-, and 18-inch diameters,
      to be installed. The pipelay barge is scheduled for nearly a
      full year of continuous operation for AIOC.
 
 "We have completed 16 months of continuous work with no
      serious incidents in the fabrication yard and on the barge",
      continued Anderson. "This is a remarkable achievement and
      we could never have reached this milestone without the committed
      efforts and hard work of our operations and project teams."
 
 "Our family of employees and associates has substantially
      increased, too. At present, more than 80 percent of our workforce
      is Azerbaijani personnel. We are proud to have experienced 'old-hands'
      like Guloghlan Nazarov working as part of our team. With this
      amount of employment of Azerbaijani personnel, we continue contributing
      to the economic development of the country by providing employment
      opportunities for Azerbaijanis," concluded Anderson.
 
 Back to Index
      AI 11.2 (Summer 2003)AI Home
      | Search | Magazine
      Choice
      | Topics
      | AI Store | Contact us
 
 Other Web sites
      created by Azerbaijan International
 AZgallery.org | AZERI.org | HAJIBEYOV.com
 |